| Description | Ledger System | Time | January | February | March | April | May | Work Day |
|---|---|---|---|---|---|---|---|---|
| Batch Interface Submission to ASD** | TempBudg Actuals | 8:30 p.m. | 06-Feb | 06-Mar | 05-Apr | 04-May | 06-Jun | 4th |
| Enter all other Temporary Budget Journals / Approve Online Financial Journals | TempBudg Actuals | 9:00 p.m. | 07-Feb | 07-Mar | 06-Apr | 07-May | 07-Jun | 5th |
| Central Allocation Processes – overhead only | Actuals | 9:00 p.m. | 08-Feb | 08-Mar | 09-Apr | 08-May | 08-Jun | 6th |
| Final Month-End Tempbudg and Actuals Data in BAIRS | TempBudg Actuals | 9:00 a.m. | 10-Feb | 12-Mar | 11-Apr | 10-May | 12-Jun | 8th |
Schedule is for both the Actuals and Tempbudg ledgers.
** This is the last day/time to submit a GL upload file to ASD. If there is a severe error, the file may not be processed in BFS-GL for the month.